Question 550 A company's continuity drill successfully activates the alternate site, but customers cannot reach the new service endpoint. What should be added to the plan? External routing, DNS/client transition and end-to-end customer access validation Only internal health checks on the backup database An assumption that clients automatically discover any changed address Removal of all customer communication during failover Explanation Correct Answer A:Internal server recovery does not guarantee delivered service. Incorrect Answers B:Customers depend on network and application paths. C:Endpoint discovery may require configured failover. D:Customers may need accurate service status and instructions.
Question 551 A backup provider reports daily successful jobs, but a ransomware recovery exercise cannot restore clean, functional systems. Which conclusion is most defensible from this evidence? The organization has not demonstrated clean end-to-end restoration and dependency recovery despite successful backup jobs The successful backup jobs prove recovery objectives are met even though the exercise failed The exercise failure proves every stored backup is corrupted and unusable The vendor’s stated recovery-time guarantee supersedes the results of the observed unsuccessful restoration Explanation Correct Answer A:Backup job completion measures creation of copies; it does not verify integrity, application dependencies or an exercisable clean recovery path. Incorrect Answers B:Job success is not evidence that a clean system can actually be restored within the approved business recovery requirements. C:The failure may arise from keys, dependencies, restore procedures or data integrity; it does not prove all copies are corrupt. D:A contractual promise cannot replace exercised recovery evidence, and the actual exercise has contradicted assumed readiness.
Question 552 An ERP requires an RPO of 10 minutes, but its last clean backup is 24 hours old. What should the DR owner conclude? An RTO of two hours automatically makes the RPO acceptable A large backup volume proves RPO compliance A policy statement overrides the actual restore point The recovery design cannot meet the approved data-loss tolerance Explanation Correct Answer D:The available recovery point exceeds the permitted loss window. Incorrect Answers A:Service downtime and data rollback are distinct. B:Capacity does not establish recovery-point freshness. C:Documented targets do not create missing transactions.
Question 553 A secondary disaster recovery facility has enough standby servers, but its power transfer switch and generators have never been exercised under the expected failover load. What should the disaster recovery manager verify? Accept the generator vendor’s capacity rating without performing an integrated site switchover Purchase more standby compute hosts before measuring the power draw of the existing recovery environment An end-to-end power switchover and sustained-load test covering facility dependencies, generator limits and required operating duration Treat a successful off-site data restore as proof that the entire recovery facility can operate during a power outage Explanation Correct Answer C:The power path is a necessary recovery dependency; its measured performance must support the business-approved continuity window. Incorrect Answers A:Nameplate capacity alone does not verify transfer equipment, combined load, fuel/runtime and actual supported service continuity. B:Additional servers can increase demand and do not demonstrate that the facility can sustain the recovery workload. D:Usable data copies do not establish availability of electrical infrastructure needed to run restored workloads.
Question 554 A bank deploys a standby database and declares the customer application recovered once replication catches up. Which DR validation is still required? Only pinging the standby server Complete application transactions, authentication and dependent-service tests through the standby path Checking the storage product license date Assuming no customer test is needed if replication reports healthy Explanation Correct Answer B:Database state alone does not prove business service recovery. Incorrect Answers A:Network reachability is not functional recovery. C:Licensing data does not prove end-to-end transaction success. D:Replication does not validate all application dependencies.
Question 555 A business uses asynchronous replication across regions and promises zero transaction loss after regional failure. What must be corrected? Increase the marketing guarantee without changing architecture Measure only the standby site's CPU capacity Align the promised RPO with possible replication lag or adopt a suitable durable design Assume asynchronous replication satisfies zero-loss recovery if the secondary region is far enough away Explanation Correct Answer C:Asynchronous replication can lose unreplicated changes. Incorrect Answers A:A larger promise does not change the lag. B:CPU metrics do not establish data consistency. D:Geographic separation can improve availability but does not remove acknowledged replication delay and uncommitted transactions.
Question 556 A security manager discovers immutable backups are stored within the same cloud account whose administrator was compromised. What should recovery architecture reconsider? Treat immutability as absolute protection against every administrative action Give the attacker-linked account additional recovery permissions Stop testing recovery because copies cannot be edited Independent administrative boundaries and tested access to protected recovery copies Explanation Correct Answer D:Immutability may not cover account-level deletion or other control-plane attack paths. Incorrect Answers A:Scope and supported immutability modes matter. B:Shared privileges increase compromise scope. C:Write protection does not prove usable restoration.
Question 557 A failover runbook starts application servers before database credentials and network policy are available. What should be corrected? Start application and database tiers together to minimize total elapsed startup time without dependency sequencing Dependency-aware recovery order and automated prerequisite validation Set recovery priorities by device serial numbers Declare the plan successful once hosts are running, regardless of failed application transactions Explanation Correct Answer B:Services often require identity, connectivity and data before startup. Incorrect Answers A:Parallel startup can fail when identity, network and database services are not yet available. C:Serials do not capture service dependencies. D:Machine uptime cannot verify that the required business service has recovered.
Question 558 A regional outage destroys both primary systems and the site's only documented recovery runbooks. What should DR readiness include? Store the runbooks in the primary-site document management service with local offline desktop shortcuts A backup of runbooks kept solely on the destroyed site Rely on emergency contacts in the same local identity directory as the destroyed site Protected accessible copies of recovery procedures and independent contact paths Explanation Correct Answer D:Documentation must remain available outside the failed environment. Incorrect Answers A:Shortcuts and the same site dependency will not provide verified access after regional loss. B:Co-located copies share the failure. C:An inaccessible directory cannot serve as the independent contact and recovery instruction channel.
Question 559 A disaster recovery exercise restores a system within its RTO but discovers missing transactions beyond its RPO. How should it be graded? RTO passed but RPO failed; require remediation of data recovery design Declare all recovery requirements passed because the service is online Ignore transactional reconciliation because it extends testing Change the approved RPO after the test without risk-owner approval Explanation Correct Answer A:Recovery time and recovery point are independent objectives. Incorrect Answers B:Operational availability does not excuse excess data loss. C:Reconciliation establishes recovered business state. D:Targets cannot be silently revised to match failure.
Question 560 A company plans to use a backup site with sufficient servers but no spare bandwidth for restored customer traffic. What should DR testing evaluate? Realistic workload throughput and external connectivity during full failover Only whether standby machines boot successfully A quote for future internet upgrades with no delivery date The number of servers with the same hostname pattern Explanation Correct Answer A:Hardware inventory does not prove service capacity. Incorrect Answers B:Boot tests omit network performance. C:Proposed capacity is not available capacity. D:Names do not establish bandwidth.