McAfee Secured

Isaca CISM Bundle

Exam Code: CISM

Exam Name Certified Information Security Manager

Certification Provider: Isaca

Isaca CISM Bundle $44.99

Pass Isaca CISM with Real Questions From Testking

Download Web's Best CISM Exam Preparation Materials Today

  • Questions & Answers

    CISM Questions & Answers

    1228 Questions & Answers

    Questions & Answers Testing Engine software allows you to practice questions and answers in real CISM exam environment.

  • CISM Video Course

    CISM Video Course

    388 Video Lectures

    CISM Video Course is developed by Isaca Professionals to help you pass CISM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Information Security Manager exam.
  • Study Guide

    CISM Study Guide

    817 PDF Pages

    Study Guide will give you a practical experience regarding the subject and provide an academic background. CISM Study Guide is available in PDF format.

Certified Information Security Manager (CISM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    1228 Questions

    $124.99
  • CISM Video Course

    Video Course

    388 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    817 PDF Pages

    $29.99

Isaca CISM Practice Test 25

Question 240

A security control is shared by two subsidiaries. One owns its technology while the other owns the sensitive information it protects. Who should approve a change that raises information risk?

  1. Let the shared technology operator approve the risk because the proposed change affects the common platform
  2. Have the hosting subsidiary approve the change and notify the other subsidiary after deployment
  3. No approval is needed because the control is already installed
  4. The designated information/business risk authority after consultation with the control owner and both subsidiaries

Explanation

Correct Answer

D:

The effect on protected information requires accountable cross-unit assessment.

Incorrect Answers

A:

The operator knows technical effects but cannot alone authorize effects on both subsidiaries’ sensitive information.

B:

Hosting ownership does not displace the other business owner’s authority over affected data and residual risk.

C:

Operational changes can alter residual risk even in an established control.

Question 241

A risk mitigation plan fails because a project sponsor changes and responsibilities are not handed over. What process would prevent recurrence?

  1. Automatically close all issues when a project sponsor leaves
  2. Make the next person to file a ticket the permanent risk owner
  3. Suspend all risk reviews until a new annual budget cycle
  4. Risk ownership transfer and acceptance of outstanding actions during governance handover

Explanation

Correct Answer

D:

Risk obligations should survive personnel and organizational transitions.

Incorrect Answers

A:

Personnel turnover does not resolve underlying exposure.

B:

Ticket creation does not establish appropriate authority.

C:

Delaying oversight leaves unresolved responsibilities unmonitored.

Question 242

An incident-response exercise shows the security team and operations team each expect the other to approve temporary network isolation. What should governance establish?

  1. Explicit crisis decision rights, risk owners and escalation thresholds for containment
  2. Give every analyst unlimited ability to isolate all critical systems
  3. Remove business leaders from crisis decisions entirely
  4. Assume the ambiguity will disappear during a real attack

Explanation

Correct Answer

A:

Ambiguous authority delays response and can create unauthorized disruption.

Incorrect Answers

B:

Unbounded authority may cause unacceptable operational harm.

C:

Business impact and safety often require their input.

D:

Unresolved exercises are evidence that response authority needs correction.

Question 243

A financial institution's risk dashboard reports only the number of vulnerability scans performed. The board needs to know if critical exposure is increasing. What should be added?

  1. Trends in material unresolved exposures, affected critical services and breaches of tolerance
  2. The number of scanner licenses purchased during the quarter
  3. A larger count of scanned low-impact laboratory machines
  4. A policy statement asserting the bank has zero acceptable vulnerabilities

Explanation

Correct Answer

A:

Risk reporting should describe business exposure and direction, not just assessment activity.

Incorrect Answers

B:

Licensing spend is not evidence of the organization's risk level.

C:

Raw coverage volume may conceal high-risk production gaps.

D:

An absolute slogan does not measure residual exposures.

Question 244

A supplier's incident rate and recovery delays have both worsened over three months, but its annual audit report was satisfactory. What is the most appropriate action?

  1. Continue using the annual report as the sole risk evidence until next year
  2. Terminate the supplier immediately without analyzing alternatives or contractual provisions
  3. Reassess residual supplier risk using current operating evidence and escalate material deterioration
  4. Treat incident statistics as irrelevant whenever a vendor holds a certificate

Explanation

Correct Answer

C:

A past assurance result does not override subsequent adverse performance.

Incorrect Answers

A:

Stale evidence can conceal an emerging dependency risk.

B:

Treatment must account for service criticality and proportionality.

D:

Certifications do not guarantee current operational performance.

Question 245

A risk treatment exception expires next month, but its control remediation remains incomplete. What should the risk-management process do?

  1. Notify the owner and approver, reassess the residual exposure and seek valid renewal or corrective action
  2. Automatically extend all exceptions indefinitely to avoid paperwork
  3. Delete the original exception record so it no longer appears overdue
  4. Assume the remediation is complete because the initial project was funded

Explanation

Correct Answer

A:

An expiring exception requires a deliberate decision before its authorization lapses.

Incorrect Answers

B:

Unreviewed extensions undermine time-limited oversight.

C:

Removing evidence cannot resolve the risk.

D:

Funding approval does not demonstrate control delivery.

Question 246

An enterprise has many green control KPIs, but ransomware recovery tests consistently exceed business outage tolerance. What should management report?

  1. The actual resilience risk and tolerance breach separately from control activity metrics
  2. Only the number of backups scheduled each night
  3. A combined average that hides the failed critical systems among healthy low-impact systems
  4. A claim that risk is low because the security dashboard is mostly green

Explanation

Correct Answer

A:

Good operational activity counts cannot negate an observed critical recovery failure.

Incorrect Answers

B:

Backup frequency does not establish restored service within target time.

C:

Aggregation can conceal material outliers requiring attention.

D:

Status colors do not override specific contradictory evidence.

Question 247

The threat landscape changes when a new exploit becomes publicly available for a widely used exposed product. What should trigger risk register reassessment?

  1. The next scheduled calendar anniversary regardless of current exploitation
  2. Only an already confirmed successful attack against the organization
  3. The number of media articles discussing unrelated software vendors
  4. A verified change in exploitability and organizational exposure relative to prior assumptions

Explanation

Correct Answer

D:

Material new threat conditions can change likelihood and treatment priority.

Incorrect Answers

A:

Time-based reviews alone may be too slow for material changes.

B:

Risk management should act before actual harm when evidence warrants it.

C:

News volume without relevant exposure is a weak trigger.

Question 248

A company's annual risk report lists issues but provides no owners or progress against response plans. What is the most useful improvement?

  1. Add decorative charts without changing the underlying fields
  2. Rank all risks only by the date they were discovered
  3. Remove unresolved risks to make the report shorter
  4. Show accountable owners, current residual risk, treatment milestones and overdue escalations

Explanation

Correct Answer

D:

Decision makers need responsibility and progress to manage exposure.

Incorrect Answers

A:

Presentation alone cannot resolve missing action accountability.

B:

Discovery order does not express treatment urgency or ownership.

C:

Omission hides exposures that still need decisions.

Question 249

A retail fraud team monitors failed login counts, but a legitimate marketing promotion also increases traffic. What is a better risk indicator?

  1. Escalate whenever failed logins exceed a fixed count, without adjusting for promotion traffic or observed compromises
  2. Contextualized account takeover signals such as abnormal success, velocity and verified fraud outcomes
  3. Track confirmed fraud losses only at month-end and discontinue near-real-time account takeover monitoring
  4. Use only website page views as the fraud risk measure

Explanation

Correct Answer

B:

A meaningful indicator distinguishes threat behavior from benign volume fluctuations.

Incorrect Answers

A:

A fixed volume threshold can mistake legitimate demand for fraud and omit subtle successful takeovers.

C:

Loss reporting is relevant, but delayed outcomes alone do not give responders timely suspicious-session context.

D:

Page views do not establish unauthorized access or financial consequences.

Question 250

A security manager discovers that multiple high-risk action plans are overdue but owners have not informed the risk committee. What should occur?

  1. Escalate missed milestones and reassess whether residual risks remain within approved tolerance
  2. Close the plans because their original due dates have passed
  3. Accept every delayed risk automatically without authorized review
  4. Replace actual completion dates with expected dates in the dashboard

Explanation

Correct Answer

A:

Overdue treatment can materially change exposure and management decisions.

Incorrect Answers

B:

Elapsed time is not remediation.

C:

A missed deadline does not confer new acceptance authority.

D:

Misreporting would undermine governance evidence.